Project Overview

Integrated communal wastewater treatment with optimised nitrification across three camp sites.

Download Case Study: EN | IND

Related Services:   Water and Wastewater Treatment Solutions

Project Title 


​​Anaerobic-Aerobic Communal WWTP Design with Optimized Ammonia Nitrification for Three Camp Sites​ 

Client: ​PT Sumbawa Timur Mining​  |  Location: Sumbawa, ​West Nusa Tenggara​ 

Sector: ​Gold Mining​ | Period / status: ​2023/ Completed​ 

Ganeca Service: ​Design, Installation, and Process Optimization of Communal WWTP (CSTP)​ 

Project Overview 


The client needed a reliable domestic wastewater treatment system to serve three operational camp sites with different daily flow rates while also meeting effluent quality standards including ammonia. Ganeca’s role was to design and optimize a Communal WWTP (CSTP) based on an anaerobic–aerobic–sedimentation–UV disinfection process that could be consistently replicated across the three flow scales. 

The Challenge 


Domestic wastewater from the camps carried a fairly high organic and ammonia load, while the camp sites were spread across different daily flow rates so a single tank size could not be used for all locations. The main challenge was keeping the nitrification process stable at low flow rates, since nitrifying bacteria grow slowly and are prone to washout without an adequate biomass-retention mechanism, as well as ensuring sludge in the sedimentation tank could be collected effectively without relying on intensive manual desludging. 

Our Solution 


Ganeca designed a four-stage Communal WWTP (equalization–anaerobic, aerobic, sedimentation, and UV disinfection) with capacity and retention time tailored to each camp site, while keeping the aerobic and sedimentation retention times consistent across all locations to maintain treatment performance. To address ammonia, a Return Activated Sludge (RAS) line was added that pumps activated sludge from the sedimentation tank designed with a sloped bottom so sludge collects by gravity toward the withdrawal point back to the aerobic tank, keeping the nitrifying bacteria population intact and allowing stable nitrification of ammonia to nitrate. The sludge age (SRT) for aerobic nitrifying bacteria was designed at 15 days to accommodate their slow growth rate and prevent washout even at low flow conditions. The sloped sedimentation tank design also reduces the need for manual desludging, since sludge collects by gravity toward the RAS pump intake. 

Results & Value 

Post-commissioning results demonstrate that system design is truly effective in the field, rather than merely a theoretical concept. The RAS and SRT configuration proved capable of maintaining nitrifying bacteria stability, ensuring effective ammonia-to-nitrate conversion, and successfully addressing the challenge of biomass washout during low-flow conditions. Laboratory test results further indicate that ammonia and organic parameters met quality standards, confirming the consistent performance of the four-stage system (equalization-anaerobic, aerobic, sedimentation, and UV disinfection) across varying flow rates at three camp locations. Additionally, the sedimentation tank's sloped design proved effective in facilitating gravity-driven sludge flow toward the RAS pump, resulting in a significant reduction in the frequency of manual sludge removal operations. 

Documentations


Communal Containerized WWTP Design – Sumbawa Timur Mining | GanecaCommunal Containerized WWTP Design – Sumbawa Timur Mining | GanecaCommunal Containerized WWTP Design – Sumbawa Timur Mining | GanecaCommunal Containerized WWTP Design – Sumbawa Timur Mining | Ganeca


Technical Resources & Downloads

Access brochures, service profiles, product specifications, monitoring-system information, and other technical resources developed to support better environmental decisions.

Still Need Help?

Tell us about your site, environmental challenge, available data, and desired outcome. Our team will help you identify the most appropriate expertise, service, or next step for your project.

Talk to Our Experts Contact Us


Business Hours

Monday -Friday (08.30 AM - 5.00 PM)